NSOL150 MAIN SPECIFICATIONS
- Usable volume: 130 L
- Configuration: monoblock, single submersible pump
- Pump power: 0.3 kW
- Impeller type: backward
- Flow rate: 20-155 L/min
- Head: 6-1 m
- Connections: inlet Ø 110 mm | outlet Ø 50 mm
- Inspection: Ø 300 mm
Pico sol lifting station 130 lt. - pump 0.3 kw

The PICO SOL NSOL150 lifting station is a one-piece system with a single submersible sewage pump, ideal when sewage needs to be pumped back to higher elevations (sewage/sewage). The pump is automatically operated by integrated float switch.
See more solutions on: sewage lifting stations.
NSOL150 MAIN SPECIFICATIONS
- Usable volume: 130 L
- Configuration: monoblock, single submersible pump
- Pump power: 0.3 kW
- Impeller type: backward
- Flow rate: 20-155 L/min
- Head: 6-1 m
- Connections: inlet Ø 110 mm | outlet Ø 50 mm
- Inspection: Ø 300 mm


PICO SOL NSOL150 is a sewage lifting station with one-piece LLDPE burying tank, PVC inlet with N.B.R. gasket and polyethylene outlet discharge. The single submersible pump is equipped with float switch for automatic start/stop.
FEATURES
- One-piece underground system with single submersible pump.
- Suitable for transferring effluent to higher elevations in civil applications.
- Automatic management by float switch.
EQUIPMENT
- One-piece container made of LLDPE.
- PVC inlet with rubber gasket N.B.R.
- Submersible sewage pump with float switch.
- Polyethylene outlet.
TECHNICAL DATA (NSOL150)
- Useful volume: 130 L
- Approximate dimensions: Ø 660 mm | H 550 mm | HE 363 mm | HU 330 mm
- Inlet connection: Ø 110 mm
- Outlet connection: Ø 50 mm
- Inspection: Ø 300 mm
- Pump: PNRG01 | Power: 0.3 kW
- Impeller: backward
- Flow rate: 20-155 L/min
- Head: 6-1 m


TECHNICAL DRAWING

INSTALLATION (OPERATING DIRECTIONS)
- Excavation with flat bottom and clear space 20-30 cm around the tank (50 cm in heavy soils/gravel).
- Bed of washed gravel 20/30 mm (15-20 cm). Forbidden to backfill with excavated material.
- Gradually fill with water and backfill with washed gravel in 15-20 cm layers.
- Final cover 30-40 cm with non-clay vegetable soil, leaving inspection plugs accessible.
- Venting: provide open vent and connect biogas vent to higher elevation of cover (piping not included).
- Manholes/pits > 50 kg: concrete slab on load-bearing soil, not on tank.

MAINTENANCE
- Periodic checks on float, pump and connections, keeping inspection accessible.
RECOMMENDED ACCESSORIES
- Biogas vent pipe (PVC/PP/PE) to the highest point of the building (not included).
- POWER (Kw)
- 0.3
- CAPACITY
- 130
Services that makes difference
24/48H shipping
Ultra-fast shipping with express courier, to offer excellent and timely service to our customers.
Secure payments
We ensure maximum security in online payments through advanced transaction protection systems for the peace of mind of our customers.
Pay in 3 installments with PayPal
Choose the convenience of paying in three interest-free installments with PayPal. An option designed for your financial flexibility.